What happened

Savannah's Cityworks history shows why a CMMS can be better understood as a relationship over time than as one purchase.

The original implementation supported Sewer and Stormwater.

The system was later expanded into Water Operations.

Later records document integration/upgrade work and migration to Cityworks Online.

What it cost

Original implementation: $384,091

Water Operations expansion: +$138,755

Integration/upgrade work: +$75,397.50

Cityworks Online migration: +$189,758

What the amount covers

These are separate events occurring at different stages of the system's lifecycle.

They should remain separate rather than being collapsed into one artificial “Savannah CMMS price.”

What it doesn’t tell us

Adding the amounts together does not necessarily establish Savannah's complete CMMS cost of ownership.

The records cover different periods, scopes and triggers.

They do not establish that another Cityworks customer will encounter the same events or amounts.

Why it matters to a buyer

CMMS cost can follow changes in the operation and technology.

Another operation joins.

Integration requirements change.

Technology architecture changes.

New cost events appear.

Buyer question:

What kinds of operational or technical changes would create additional paid work after we go live?

Primary evidence

2017 expansion:
City of Savannah 2017 agenda

2021 integration/upgrade:
City of Savannah 2021 agenda item

2024 Cityworks Online migration:
City of Savannah 2024 agenda item